A Bristol Construction Company Who Was Almost A Year Late On An 11-Million Dollar 2016 Johnson City Project Will Forfeit Just Over 293-Thousand Dollars. Frizzell Construction Was 350 Days Late On A Project To Renovate The Knob Creek And Brush Creek Wastewater Treatment Plants. The Project Was Supposed To Be Completed In 700 Days.